A stair is a walking part, a structure and a railing system. Learn the names before anyone asks for “stair parts.”
In this lesson9 sections
- What are the walking and structural parts of a stair?
- What are the parts of a stair railing?
- Does the rail go over the posts or between them?
- Which stair parts have to come from the same system?
- Who decides the heights and the spacing?
- Ask about the finished floors before the stair order
- What to ask the customer
- What stays product-specific
- What to do next
A stair is a walking part, a structure and a railing system. Learn the names before anyone asks for “stair parts.”
A stair has three groups of parts. The walking parts are the treads, the risers and the nosings. The structure is the stringers. The railing is a system the stair industry calls the balustrade: newel posts, handrail, balusters and the fittings that join them. When a customer asks for “stair parts,” find out which group they mean, and ask for the plans, because sizes, heights and spacing come from the stair design and the building code.
This page uses the definitions of the Stairbuilders and Manufacturers Association (SMA), the stair industry’s trade group. It also uses one stair parts maker’s own guidance. Millwork 101 gave you the short list. This one goes a level deeper.
What are the walking and structural parts of a stair?
| Part | What it is | Watch for |
|---|---|---|
| Tread | The horizontal walking surface of a stair | Material, thickness and nosing profile are separate choices |
| Riser | The vertical part of a step, in the space between the treads | An open-riser stair has no riser boards |
| Rise | The vertical distance between the leading edges of adjacent treads | A distance, not a part; codes call it riser height |
| Total rise | The height of a stairway from finished floor to finished floor | Changes when the flooring changes |
| Run | The horizontal distance between two nosings | Also set by the design and the code |
| Nosing | The leading edge of a tread or landing | Landing nosing is sold as its own moulding |
| Stringer | The inclined members the treads attach to, carrying the stair’s load to the building | Structure: not a trim piece |
| Skirt board | A non-structural trim board along the side of the stair that the treads and risers fit to | Looks like a stringer, is trim |
| Landing | The walking surface at the top and bottom of a flight, or a platform between flights | Landings get their own newels and nosing |
| Flight | An uninterrupted series of steps from one landing to the next | A stair can have several flights |
Wording summarized from the SMA glossary. The stair design decides every dimension.
Word to know
The whole glossary- Open and closed stringer
- An open stringer is cut or notched along its top edge so the treads sit on it and their ends show. A closed stringer encloses the ends of the treads and risers.
What are the parts of a stair railing?
The railing is a balustrade: a system of rails, newels, balusters, panels or other parts. Where it keeps people from falling, it is also a guard. Three parts carry most of the names.
A vertical element or post used to connect balustrade components to the structure of a stair or floor system
A sloped or horizontal rail intended for grasping by the hand as an assist for guidance, support, pulling, or arresting a fall
A vertical member used as in-fill to limit the size of openings within a balustrade
Many customers call balusters spindles. Newels come in kinds named for where they stand. The starting newel is at the bottom of the stair. Landing newels are at landings and balconies.
Fittings and the words that come with them
- Fitting: a rail piece profiled to match the rail, used where the rail changes direction or height, or for ornament.
- Volute: a starting fitting that spirals, seen from above, at the bottom of the rail.
- Turnout: a starting fitting that turns 90 degrees toward the starting newel.
- Gooseneck: the combination of easings, rail and caps that carries a sloped rail into a level rail, at the top of a flight or through a turn.
- Easing: a curve in the rail in place of a sharp angle.
- Rosette: the decorative plate that anchors the end of a rail where it meets a wall.
- Plowed rail and fillet: a rail with a groove cut in its bottom to take square-top balusters, and the thin strip that fills the groove between them.
Does the rail go over the posts or between them?
There are two ways to build the railing. In an over-the-post system, fittings carry one continuous handrail over the tops of the newel posts. In the other, which the SMA glossary calls post-to-post, the rail is interrupted by the newels and stops at the side of each post. The choice changes which newels, fittings and caps go on the order. So settle it before you count parts.
Which stair parts have to come from the same system?
The ones that touch. Baluster tops have to fit the rail. Newels have to fit the fittings. The look has to match from the first step to the balcony. L.J. Smith Stair Systems, a stair parts maker, shows how much detail sits behind one baluster.
LJ line has 3 lengths, trimmed from the bottom for length, and the bottom blocks flow with rake of the stair.
Its other line, the S line, comes in five lengths trimmed from the top. Its bottom blocks line up evenly with each step. The same maker says square-top wood balusters go into plowed rail, set with glue and toenails, with fillet between them to hide the nails. And on iron balusters it is plain about mixing.
We do not recommend mixing them on the same job because the details and the finishes may not match between the solid balusters and the hollow balusters.
If one maker advises against mixing two of its own iron baluster types on one job, do not assume two makers’ parts will match. For a repair, get the maker and the style, or a sample, before you quote.
Who decides the heights and the spacing?
Not the counter. Riser height, tread depth, handrail height, guard height and how far apart balusters may be are set by the building code for that job, and the stair design follows it. Even the baluster maker works from the code: L.J. Smith’s method for how many balusters go on a tread starts from the maximum spacing permitted. Quote from the plans or the builder’s numbers, write down who gave them, and never from a customer’s guess.
Ask about the finished floors before the stair order
A stair is drawn from finished floor to finished floor, so anything that changes a floor changes the stair. If thicker flooring goes in at the bottom than the stair was laid out for, and the treads and the upper landing stay where they were, the first step comes out shorter than the rest. That is a problem for the stair builder and the designer to solve before parts are cut, not something to fix at the counter or on site. So before a stair order goes in, ask what the finished floors are, top and bottom, and whether they have changed since the plans were drawn. Write the answer on the quote.
What to ask the customer
“Is this a new stair or a remodel? Do you have the plans or a drawing? Is it the treads, the railing or both? Open or closed risers? What flooring is at the top and bottom, and is any of it changing? Does the rail run over the posts or stop at them? Can you send photos of the bottom post, the landing and where a spindle meets the rail? Who is building it, and who checked the code?”
Checklist: before you quote stair parts
Go down this list before you quote stair parts. Any box you can’t tick is the step to go back to.
0 of 9 ticked
What stays product-specific
Lengths, squares, rail profiles, fittings, how a newel is attached and how balusters are fastened belong to each maker’s system and instructions. The numbers that keep people safe come from the code and the stair design. This page teaches the names so you can ask the right questions.
What to do next
Find the nearest stair with a railing, at work, at home or in a model home. Name every part out loud: treads, risers, nosing, skirt board, starting newel, handrail, fittings, balusters. Then pull your supplier’s stair parts catalog and find the balusters that fit its plowed rail.
Stair parts ride along in house packs. You can see that in the trim pack at Magbee Contractors Supply. Next on this path: TFL, HPL, MDF, or Plywood. Back to the trim package: Casing, Base and Crown. Deck railing words are in Decking 101, and every term is in the Building Industry Glossary.
Questions people ask
What is the difference between a riser and rise?
A riser is the board, the vertical part of a step between two treads. Rise is a distance, the height from the front edge of one tread to the next, and building codes call it riser height. A stair can have open risers, with no board, and still have a rise.
What is the difference between a handrail and a guard?
A handrail is the rail you hold for support going up and down. A guard is the barrier along an open edge that keeps people from falling. One railing can do both jobs, but a rail that looks solid is not automatically an acceptable handrail. The plans and the local code decide what is required.
How do I order replacement balusters?
Bring a sample or the exact maker and style, the length, the size of the square at the top and bottom, and whether the top goes into a plowed rail or is pinned. Makers trim their lines differently: L.J. Smith trims one baluster line from the bottom and another from the top. Mixing lines or makers on one stair can mean the details do not match.
What is a newel post?
The post that connects the railing to the structure of the stair or floor. The starting newel is at the bottom of the stair, and landing newels sit at landings and balconies. How a newel is attached is a structural detail from the maker’s instructions and the stair design.
Episodes in this piece
Sources
- Glossary Stairbuilders and Manufacturers Association (SMA)
- Balusters: Frequently Asked Questions L.J. Smith Stair Systems
- How a 70 Year Old Millwork Shop Operates: Behind The Build at Magbee Contractors Supply Grit Guide