Every truss is designed for one spot on one house. The order is won on a fast quote and lost on a missing heel height.

A truss order is a design job before it is a delivery. The dealer sends the plans to a truss plant, a truss technician lays out every truss and designs each one for its spot, the builder approves the layout and price, and only then does the plant build and ship the package with its drawings. Your part at the counter is to get the plans and the missing details to the plant fast, and to make sure nothing on the roof gets decided by guessing.

This lesson follows one truss order from plans to jobsite, with the words a truss plant uses. It builds on Lumber Sizes, Grades and Stamps and Engineered Wood.

What is a roof truss?

A roof truss is a factory-built frame of lumber held together by metal plates. The Structural Building Components Association (SBCA) defines a metal plate connected wood truss as an “engineered, pre-fabricated structural component, assembled from wood members and metal connector plates,” with members that “are usually assembled such that the members form triangles.”

The parts of a truss, in SBCA’s words
PartWhat it is
Top chord“Inclined or horizontal member(s) that establishes the top edge of a truss”
Bottom chordThe member(s) “that defines the lower edge of a truss”
WebA “member that joins the top and bottom chords to form the triangular patterns typical of trusses”
Truss plateA steel connector plate with “integral teeth,” pressed into the wood at each joint
Panel pointWhere webs meet a chord and are joined by plates
Heel height“Vertical depth of the truss at the outside face of bearing”
OverhangThe part of the truss past the outside bearing that makes the eave
Girder trussA truss “designed to carry loads from other structural members framing into it”
Gable end frameThe piece that completes an end wall, with vertical members for sheathing

Definitions from SBCA’s terminology and roof truss pages. The names on a real job come from that job’s truss drawings.

Floor trusses are built the same way with flat, parallel chords. At Harbin Lumber in Lavonia, Georgia, the plant builds both. In our Behind the Build visit, Westley Harbin stopped at a stack of 24-inch-deep floor trusses and explained that depth is a design answer: “When you’re talking about the depth that pretty much all relates to a span scenario” (22:38).

Who designs a truss?

Two people, with two different jobs. SBCA defines the building designer as the owner or the person hired by the owner who “is responsible for the preparation of the construction documents.” The truss designer is the person “responsible for the design of the individual truss members and preparation of the truss design drawings.”

The dealer is in the middle. You carry the plans one way and the drawings and questions back.

Truss design drawing (TDD)
The drawing for one truss: SBCA calls it a “written, graphic and pictorial depiction of an individual truss that includes information required in ANSI/TPI 1.”
Truss placement diagram (TPD)
The roof plan showing where each truss goes: an “illustration identifying the assumed location of each truss.”
Truss submittal package
Every truss design drawing plus, as needed, the placement diagram, a cover sheet, and the bracing details. This is the paperwork that goes with the trusses.

How does a truss order work?

A truss order works in seven steps. The steps are a teaching summary built from SBCA’s definitions and the Harbin visit. Your plant’s own process and forms come first.

  1. Plans in. The builder or dealer sends current plans: roof plan, wall plan, sections and the roof pitch.
  2. Questions out. The truss technician asks for anything the plans leave open: bearing walls, heel height, overhang, ceiling shapes such as vaults, attic space, and loads like a water heater or HVAC unit in the attic.
  3. Layout and quote. The plant draws the placement diagram, designs each truss and prices the package.
  4. Approval. The builder signs off on the layout and price. Any change after this point means a new layout.
  5. Build. The plant cuts lumber, sets up each profile on a table and presses the plates.
  6. Delivery. The package ships with the submittal package. Ask about site access and where the trusses will be set down.
  7. On the job. The installer works from the truss drawings and the placement diagram.

What a truss plant checks before it ships

Harbin builds on auto-set tables: when one truss is done, the operator presses a button and the stops move to set up the profile of the next one. After pressing, the plant stands its trusses up instead of stacking them flat, and Westley Harbin explained why. The plate on the bottom side of a truss is the one that is easy to miss or set crooked. Standing the truss up lets the crew see it.

They're now looking at the underside or the back side of the truss. So, it's just a third party quality or it's a quality check for them to go through and look, hey, are all the plates in the right orientation.

Westley HarbinFourth generation, Harbin LumberFrom our Behind the Build visit, at 33:38

Size matters at the jobsite too. One truss for a vaulted ceiling, he said, “probably weighs about 250 or 300 lbs” (34:18). Watch the short clip: Why you should stack roof trusses vertically. The plant’s old and new tables are in Truss building then vs. now.

What goes wrong on a truss order

  • The heel was never defined. SBCA: “If the heel is not specified on the construction documents, the truss technician is required to scale the heel height from a section view, which can be less than desirable for accuracy.” The heel sets the roof height and the room for insulation at the wall.
  • Bearing changed. SBCA notes that if the bearing size varies from the truss design, finish work at the wall can be affected. A moved wall is a new design question.
  • Changes after the design. Any question about changing a truss goes to the truss designer.
  • Stacked flat in the mud. Storage and lifting belong to the installer’s guide, BCSI. Ask where the trusses will sit before they go up.

Ask for the heel height on the first call

Speed is one of Harbin Lumber’s working goals, and Westley Harbin described what builders ask him every day: “So, hey, how fast can you turn my quote around?” (18:28). In production building, he said, “it’s almost all truss” (21:50).

Speed wins the truss quote. The questions you ask before it goes to the plant decide whether the package fits. On a truss order the missing details have names: heel height, bearing walls, overhang, attic loads, ceiling shape. Ask for them on the first call.

What to ask before you send plans to the truss plant

“Are these the current plans, with the date? What roof pitch and overhang? What heel height, or how much insulation at the wall? Which walls are bearing? Any vaults, trays or attic rooms? Anything heavy going in the attic? Where will the truck set the trusses, and who is installing them?”

Checklist: A truss order is ready for the plant when

Tick each one off. It is not ready until every box is ticked.

What to do next

Ask your truss supplier for one finished submittal package from a past job. Find the placement diagram and one truss design drawing. Then find the heel height on that drawing.

Next: OSB vs Plywood: Sheathing and Subfloor Stamps, the panels that go on top of the trusses.

Questions people ask

What is the difference between a truss and a rafter?

A rafter is one sloping framing member. A truss is an engineered assembly of chords and webs joined by metal connector plates, designed so its parts work together. Its chords, webs and plates are designed as one piece.

What is a truss placement diagram?

SBCA defines it as the “illustration identifying the assumed location of each truss.” It is the plan the installer follows. Each truss also has its own truss design drawing, and together with bracing details they make the truss submittal package.

Can a web be cut to fit a duct or an attic stair?

Ask first. A cut or changed truss is a question for the truss designer and the building designer.

Episodes in this piece

Sources

  1. Terminology (truss parts, truss design drawing, truss placement diagram, truss submittal package, building designer, truss designer) Structural Building Components Association (SBCA)
  2. Roof Trusses (bottom chord, heel, overhang, continuous lateral restraint, bracing) Structural Building Components Association (SBCA)
  3. Georgia Builders Are Powered By This Fourth Generation Lumberyard | Behind the Build: Harbin Lumber Grit Guide
  4. Why you should stack roof trusses vertically Grit Guide

Also named on this page

People and companies mentioned above, each with a page on Grit Guide.