How a Lumberyard Cut Truck Turnaround From 52 Minutes to 12
Russ Kathrein’s yards got there by asking drivers where the time went. Scott Morrison of Do it Best uses the same idea on picking and layout. He says one member got 90 minutes of its day back.
Client: Do it Best is a Grit Blueprint client.
One chain of lumberyards cut its truck turnaround from 52 minutes to 12 in about three months. It did this with no new trucks and no new people. Russ Kathrein, now vice president of lumber and building materials at Do it Best Group, ran those yards.
His team asked the drivers and the yard crew where the time went. Then the team fixed the waits. It added an alert 10 minutes out and staged the next load before the truck pulled in. It also added a marked parking spot and one shelf of driver supplies.
It started by accident. A lean consultant was at one of Kathrein’s yards to work on something else. Lean is a way of running an operation that hunts for wasted time and wasted steps. While he was there, he started timing the delivery trucks. He timed how long it took a truck to come back into the yard, get its next load and leave. That is truck turnaround. The answer was 52 minutes.
Some of Kathrein’s yards were in metro areas where the trucks were always busy. He and his team sat down and asked what a 30-minute turnaround would be worth. Their answer, he says, was $1.6 million more material delivered in a year (14:13).
Who knows where truck turnaround time goes?
The drivers and the yard crew do. The fix was not drawn up in an office. “We got the drivers involved, we got the yard guys involved,” Kathrein says (14:35). Then they asked them for their pain points and worked on what came back.
What the yards changed
- A 10-minute warning. The yards were geofenced about 10 minutes out. A geofence is a virtual line on a map that sends an alert when a vehicle crosses it. When a truck crossed, the delivery software pinged the dispatcher that it was inbound.
- The next load ready first. The dispatcher told the forklift drivers, and they had the material waiting.
- A marked parking space. The driver pulled into a designated spot and walked in for the paperwork. The forklifts, Kathrein says, “would be swarming the truck and loading it while the driver walked in to get his paperwork” (15:06).
- A driver supply shelf. Drivers said they lost time hunting for washer fluid, straps, flags and pencils. The yard filled a four-by-eight set of shelves with everything a driver needs, in one place.
- Help with the straps. The yard crew helped strap the load, and the truck was gone.
What happened
“We blew through 30 minutes,” Kathrein says (15:50). After the first month the yards were down to 20. Within another month or two they were averaging 12. From 52 minutes to 12, with no new trucks and no new people.
The drivers loved it, he says. They were busy, and they were no longer wandering the yard looking for product. They also liked the contest. The yards started competing with each other for the best turnaround time.
“If I were king”
“I think the biggest problem we run into as managers is we feel like we’ve got to bring all the solutions,” Kathrein says (17:06).
He tells a story from his father’s lumberyard. Yard foremen kept coming and going. A quiet worker who had started there at 18 watched every one of them. When Kathrein ran out of options and asked him to take the job, “in a week, that yard was spotless” (17:37).
“I think that guy walked around for five years and said, you know, if I were king, I’d do it this way, but no one ever asked him,” Kathrein says (18:02). Ten years later the man was still the foreman.
What is zone picking, and why does it save time?
Zone picking splits a yard or warehouse into smaller areas, and each person pulls material from one area to a common spot. It saves the walking. Scott Morrison is an industrial engineer and the operations excellence manager at Do it Best. He works on site in lumberyards, door shops, truss plants and wall panel plants. His target is the time between tasks. “It’s the steps and the motions that are in between the activities. That’s what you’re really attacking,” he says (5:06).
When a crew asks him to make something go faster, his answer is to move it closer. Cut the distance in half and you get the effect of working twice as fast.
Picking is pulling the material for an order. The usual way is to hand someone the ticket and send them around the whole facility to find everything. Zone picking was one of his recent projects.
Morrison says one Do it Best member that made the change is saving 90 minutes a day. “They were finishing up at five o’clock and now they’re finishing at 3:30,” he says (7:15). That means less overtime. It also means the trucks are loaded the night before and ready to leave at 6:30 or 7:00 the next morning. “First outs are critical,” he says (7:54). A first out is the first delivery of the day, the one a builder’s crew is standing by for.
How Morrison runs a project
- He starts with an honest picture. He maps what he calls the current state, with the crew telling him the problems “warts and all.” His reason: “If you don’t start with a problem statement that’s accurate, you’re gonna solve the wrong problem or not solve the problem at all” (3:05).
- He puts a mixed team in the room. A site leader he calls the quarterback, someone from operations, someone from sales or the office, and people from the yard or the shop. It cannot be all one level of management.
- He expects the first plan to be hated. Teams often dislike the first new layout, he says. By the third or fourth version they have helped make it, and they own it.
- He asks where the business wants to be in two to five years. On one warehouse project the owners told him they planned to grow. So he did not fill the 45,000-square-foot building. His layout fit everything they wanted and left room for about 50% growth.
Take out the waiting before you tell anyone to hurry
Speed in a lumberyard rarely comes from telling people to hurry. Kathrein’s yards took out the waiting, the walking and the hunting, and nobody had to drive faster.
So pick one constraint, the biggest thing holding the trucks back, and fix only that. Measure it, then choose the next one. Ask the people closest to it before you draw anything. When the same delay keeps showing up, follow the work from the gate to the loaded truck. Look for the step that depends on someone remembering, walking or waiting.
On the Morrison episode, Stefanie Couch, host of the Grit Blueprint Podcast, put the door shop version as a question. It was about an assembly-line operator who walks for every insert or threshold: “if you could make that where they turn around and grab it without taking a step, how many hours in a week could that save?” (4:33). Kathrein’s quiet foreman had the answer for five years. Asking cost nothing.
What to do next
- Time ten truck turnarounds this week, from the moment the truck pulls in until it pulls out loaded. Write down the average.
- Ask your drivers and yard crew where they wait and what they go looking for.
- Pick one fix and run it for a month. You could stage the next load before the truck arrives. Or you could stock a driver supply shelf next to dispatch.
- Follow one pick ticket through the yard and count the trips. Ask whether zones and one common staging spot would cut them.
- Share the turnaround number with the crews every week. Kathrein’s yards competed on it.
For the people side of a faster yard, read How to Make Sure Every Employee Knows the Goal. Kathrein’s other habits for cash, billing and dead stock are in Why Russ Kathrein Bills a Special Order the Day It Lands. A new hire’s view of the yard is in Your First 30 Days at a Building Materials Dealer.
The interview with Scott Morrison was recorded for an episode sponsored by Do it Best Group.
Questions people ask
What is truck turnaround time at a lumberyard?
It is the time from a delivery truck pulling back into the yard until it leaves again with its next load. Russ Kathrein’s yards measured 52 minutes when a lean consultant first timed it. Time ten trucks yourself to get your own number.
How do you cut truck turnaround without adding trucks or people?
Take out the waiting. Kathrein’s yards sent dispatch an alert when a truck was 10 minutes out, staged the next load before it arrived, gave drivers a marked spot and one shelf of supplies, and had the yard crew help with straps. They went from 52 minutes to an average of 12.
Why look at the steps between tasks instead of asking people to work faster?
Because the walking and waiting between tasks take time without adding anything. Scott Morrison of Do it Best says cutting the distance in half has the effect of working twice as fast. Where you put the work and the material often matters more than how hard people push.
What is zone picking?
Zone picking breaks a yard or warehouse into smaller areas. Each person picks the material from one area and brings it to a common staging spot, instead of one person walking the whole facility for every ticket. Morrison says one Do it Best member that switched saves 90 minutes a day.
Who should be involved in a yard or door shop layout project?
The people who do the work, plus a site leader, someone from operations and someone from sales or the office. Morrison starts by mapping the current state with the crew, problems and all, so the team solves the right problem and owns the new layout.
Watch the full interviews
Simple Ways to Create Cashflow in Your Business with Russ Kathrein, and Designing Efficient Yards and Door Shops for Speed, Safety, and Growth with Scott Morrison. Time stamps are from the podcast audio.
Scott Morrison of Do it Best explains how lumberyards and door shops get faster by mapping the work, cutting the steps between tasks and picking by zone. One member's zone picking change saved 90 minutes a day.
A Grit Guide original. This piece is built from our own interview.